Stormwater project up for approval without pedestrian bridge, trees, or promise of a new aboiteau

A black and white map showing a proposed stormwater retention area in Sackville. There is an orange area circled on the right of the map.
Drawings of the proposed stormwater retention pond between Charles Street and Sloan Drive. Source: Englobe Engineering.
Erica Butler - CHMA - SackvilleNB | 14-02-2023
Share on facebook
Share on twitter
Share on linkedin
Share on pinterest
Share on email
Share on print

The province of New Brunswick says it has not committed to replacing an aboiteau that would play a key role in draining a multi-million floodwater system slated to be completed in Sackville by the end of this year.

The engineer heading up the final phase of the Lorne Street Floodwater Mitigation project was in Sackville town hall on Monday to give Tantramar council an overview of the project.

At their meeting on Tuesday, Council will be asked to approve paying Beale and Inch Construction just over $5 million to complete the project, which involves digging a third retention pond on the far side of Charles Street, and channeling water under roads and the CN rail line out to the Tantramar River. That’s where the water would flow out through an aboiteau owned by the province, which lets fresh water flow out into the river, but blocks tidal water from flowing in.

Unlike the last time he appeared before council, project lead Pierre Plourde of Englobe Engineering seemed confident that the replacement of the aboiteau was not a dealbreaker for the project to work.

“Our stormwater strategy is somewhat dependent on that aboiteau, but not entirely,” Plourde told council. “What will happen when the aboiteau is upgraded in the future, it will allow the water to move faster within the system. Right now, we’re a little bit restricted by that aboiteau, but we can still go full force with the strategy.”

The town had hoped the Department of Transportation and Infrastructure (DTI) would install a larger aboiteau at a lower elevation which would help the water drain more quickly from the retention pond system. Plourde said the former minister of DTI, Jill Green, had toured the site in the summer. “It was a really good meeting,” recounted Plourde. “They understand that something needs to be done. We just don’t have a timeframe yet from them.”

In an email response to CHMA on Monday, DTI communications staff said they are aware of the Tantramar proposal, but have made “no commitment at this time.”

Town engineer Jon Eppell said on Monday that while a bigger and lower elevation aboiteau would be desirable, it’s not the end of the world if it does not happen. Eppell said the new flood control system will still work with the old aboiteau, which might only pose a problem in the event of two massive storms, back to back.

In Plourde’s presentation Monday, he harkened back to the first planning years of the project, recalling the flooding events that inspired the plan.

“The flood water was basically eight inches below the stop sign on the road,” said Plourde, referring to the vicinity of Lorne Street and St. James. Plourde said the chosen strategy was to create retention ponds. “When it rains, we need to be able to take some of the water and store it in stormwater retention ponds, just to make sure that the when the storm goes away, and the tide goes down, we’re able to push that water back to Tantramar river,” said Plourde.

Pedestrian bridge, trees removed to meet budget

Jon Eppell also took some time Monday to explain recommended changes to the scope of the work for phase III of the stormwater project, to help it fit Tantramar’s approved budget.

Although Beale and Inch’s bid was the lowest, it still came in about $500,000 over what the former town of Sackville had approved. In order to get the price down, Eppell is recommending that Tantramar council approve the project without some components. Two pedestrian bridges to connect the circular pathway around the pond will be excluded, as will a number of trees and shrubs that were to be planted on the grounds. Beale and Inch will also be permitted to begin the project later than planned, waiting until early summer, when the ground has had a chance to dry out. Those combined changes, “brought us back within budget,” Eppell told council. “We are headed down the path of recommending that we proceed on the basis of the reduced scope, keeping in mind that we can add that in later if funding can be found.”

Tantramar council meets Tuesday night at 7 p.m. at Sackville town hall, and on the agenda is the approval of a $5 million tender for the construction of phase III of the Lorne Street Stormwater Mitigation project.

Listen to the CHMA story below: